 |
 |
|
|
| |
|
|
| |
 |
NORS Tunnel, Los Angeles, CA
Excavation by means of a digger
shield TBM and EPB machine for the 48,000 ft of main line and
diversion sewer tunnels and accompanying structures included tunneling
through two areas of contaminated ground where special mining
techniques and environmental precautions were necessary.
Our responsibilities included evaluation of
claims, monitoring of excavation and construction, negotiation
of change orders, design and inspection of chemical grouting for
contaminated ground water, working with state and local agencies
to obtain permits to excavate through contaminated ground, review
of contractors' submittals and assistance to the owner.
|
| |
|
|
| |
 |
MUNI Metro Turnback Project, San Francisco,
CA
This project involved the excavation
of two 840 foot, 18-foot diameter transit tunnels using compressed
air, through fill material composed of sand and soft clay, with
four zones that were chemically grouted.
We provided tunnel engineering and construction
management, the responsibilities of which included all facets
of tunnel, shaft, and chemical grouting: constructability review,
submittal review, evaluation of claims, daily inspections, daily
interface with contractor's project manager and superintendent,
monitoring work progress, instrumentation monitoring and evaluation,
safety, negotiation of change orders, verifying contractors, monthly
progress invoices, monitoring and revising schedule, and preparing
final as-built report.
|
| |
|
|
| |
 |
Brushy Creek Interceptor, Round Rock,
TX
Brushy Creek Regional Interceptor
consists of approximately 7,000 feet of 110-inch initial diameter
machine bored tunnel. The tunnel will be constructed in a stiff,
expansive clay and a competent limestone. A complex fault zone
marking the contact between the two formations will be crossed.
Brierley Associates and PBS&J designed the
tunnel alignment and grade. Brierley Associates performed the
geotechnical evaluation, prepared the Geotechnical Baseline Report,
assisted in preparing the contract specifications, and prepared
the initial tunnel support design, in addition to providing Construction
Management services during the project construction.
|
| |
|
|
| |
 |
South Austin Regional Wastewater Treatment
Plant, Austin, TX
The Lift Station Interconnect Tunnel
Project, part of a plan to expand and improve the South Austin
Regional Wastewater Treatment Plant, consists of two tunnels and
associated access shafts, the first of which is a 1,270-foot long,
60-inch diameter conduit that will allow water to flow between
two lift stations, and the second is approximately 526 feet long
with a finished diameter of 60 inches.
The owner, the City of Austin, contracted Turner
Collie & Braden as the prime design firm, with Fugro South
Inc. and Brierley Associates as sub-contractors to prepare the
GBR, assist with the preparation of other contract documents,
and provide on-site technical support during tunnel construction.
|
| |
|
|
|